Schreiner calls on Ombudsman to enter issue

Ontario Green Party Leader Michael Schreiner Schreiner said in his statement. released a statement Friday, calling on Ontario Ombudsman André Marin for a review of the procurement process and the bids that were submitted in that procurement process for the gas peaker plant slated to go in the Holland Marsh

The plant is slated to be built by York Energy Centre (Pristine Power).

“I have asked the Ombudsman to ascertain whether the requirements of the RFP were met by the Ontario Power Authority and by the successful proponent, whether the OPA abided by the government of Ontario’s procurement policy and honoured the public undertakings and commitments it made with respect to the procurement process,”